Paymo Logo
Blog Home
Work Management
Last modified date

Aug 5, 2022

Task Dependencies

author image

Laurentiu Bancu

Blog average read time

2 min

Last modified date

August 5, 2022


A Gantt Chart is simple to read and understand, but it can’t be done without understanding task dependencies. These are basically logical relationships between tasks or activities. There are four types of dependencies, and in this article, we’ll talk in detail about all of them. The dependent tasks are predecessor and successor. The predecessor task determines the start or finish date of its successor task. When you create the “dependency line” between 2 tasks, you always start with the predecessor.

NOTE: If you’re a project manager looking for the best tools for timekeeping or just a way to track hours, check out these top time tracking software. It also works great if you’re a small business owner or if you’re looking for the best time tracking solution for lawyers, accountants, and consultants. Also, if you want a simple task list tool for personal use or professional use, read this article about the best task management programs.

Finish to start (FS)

This dependency is the default one, because is the most common you’re going to use in your projects. In this scenario, the predecessor task must finish before the successor can start (but it might start at a later date).

Let’s assume you’re a design agency and you’ve received a job to build a website. You can’t start creating the plan (successor) before you finish the meeting with the client (predecessor). Only after you’ve met with the client and learned all the details about the project you can start working on your plan. It’s not necessarily to start working on the plan right away, but the predecessor task has to be completed first.

Finish to start dependency

Finish to finish (FF)

In this case a task cannot end before the predecessor ends (but it might end later). Let’s see an example of this type of dependency in our design project. At some point, the designer will start working on each page of the website and create PSD files. These files are sent to the front-end developer who has to create these pages and implement the design. The developer’s job cannot finish before the designer has finished creating the design for all pages (so it cannot finish before the 23rd).

Finish to finish dependency

Start your free Paymo trial to test out the Gantt Chart feature on your own projects.

Start to start (SS)

The “Start to Start” dependency says that a task cannot start before the predecessor starts (but it might start later). Now let’s see how this can be applied in our project. In order for the designer to start working on how each page will look, he needs wireframes of those pages, which means that he can’t start working on design before the job of creating the wireframes has started.

Start to start dependency

Start to finish (SF)

One peculiar dependency, which is rarely used, is “start to finish”. In this case, the predecessor must start before the successor can finish. For our project an “extreme” example would be the situation where you’re looking to hire a full-time designer for your agency, which you didn’t find yet, but because you can’t afford to delay the project, you temporarily hire a freelance designer to perform the job, which means he can’t leave before the full-time designer comes.  As already mentioned, you shouldn’t worry if this seems confusing, because you won’t meet with this type of dependency very often.

Start to finish dependency

As a rule of thumb, a good practice is to stick with the common FS dependency or else you run into the risk of creating a very confusing plan (chart).

 

Found this article useful? Please spread the knowledge and share it with your teammates and followers.

Read More

August 19, 2022

Read time clock

17 min

8 Gantt Chart Software Worth a Look in 2022

Author: Marcel Tit

Marcel Tit

September 16, 2022

Read time clock

16 min

Best 21 Idea Board Software For 2022

Author: Alexandra Martin

Alexandra Martin

September 16, 2022

Read time clock

36 min

The Best Project Management Tools You Can Try in 2022

Author: Marcel Tit

Marcel Tit

Paymo
HomeComplete Feature ListPricingFree AccountAbout Us

‾‾‾‾‾

Contact SalesOnboarding

‾‾‾‾‾

CustomersTestimonialsSpread the WordAffiliates

Paymo Logo

Copyright © 2022 Paymo LLC

By signing up, you're agreeing with the Paymo Terms of Service and Privacy Policy

Cookies help us deliver our services. By continuing to use the website, you consent to the use of cookies.

Learn more about the cookies in Our Privacy Policy.